What is construction adjudication, and how does a small firm start one?

By ·AI-assisted·Editorial policy

Adjudication is a fast, statutory way to settle a dispute under a construction contract. Either party can start it at any time by giving notice. The adjudicator should be appointed and the dispute referred within 7 days, and the decision is due within 28 days of referral. It binds both sides until a court, arbitration or agreement settles the dispute.

Page of an EstiMate sample quote listing steel beams, columns and masonry with a picture, description, quantity, unit price and total on each line, and the working shown for the brick quantities
Sample quote: materials

It was designed for exactly the disputes small firms have: unpaid applications, disputed variations and withheld retention.

Who has the right to adjudicate?

Section 108 of the Housing Grants, Construction and Regeneration Act 1996 gives the right to any party to a construction contract. The Act says "dispute" includes any difference, so it doesn't have to be a large or formal row.

If your contract doesn't meet the section's requirements, the adjudication rules in the Scheme for Construction Contracts apply instead.

Does it apply to homeowner work?

Not as a statutory right. Section 106 takes contracts with a residential occupier outside Part II of the Act, so a homeowner client isn't bound by it. Your written contract with them could still include an adjudication clause.

What goes in a notice of adjudication?

Under the Scheme, the notice must go to every other party to the contract and briefly set out:

  • the nature of the dispute and the parties involved
  • where and when the dispute arose
  • what you're asking for, such as payment of a sum
  • the names and addresses of the parties

Keep it short and precise. The adjudicator can only decide the dispute you've described, so describe it carefully.

How is the adjudicator chosen?

The Scheme sets an order. First, the person named in the contract. If there isn't one, the nominating body named in the contract. If neither applies, you ask an adjudicator nominating body to select someone.

Send a copy of the notice of adjudication with the request. The person asked must say within two days whether they're willing to act.

What is the referral notice?

Within seven days of the notice of adjudication, you send the adjudicator your referral notice: the case in writing. Include copies of the contract, or the relevant parts, and the documents you rely on.

Send copies of everything to every other party at the same time. The adjudicator then tells everyone the date the referral arrived.

How long does it take?

Under the Scheme, the decision is due 28 days after the referral notice is received. It can be 42 days if the referring party agrees, or longer if both parties agree after the referral.

The adjudicator can take the initiative in finding out the facts and the law, and must act impartially.

Is the adjudicator's decision binding?

Section 108(3) says the decision binds the parties until the dispute is finally decided by legal proceedings, by arbitration if the contract provides for it, or by agreement. The parties can also agree to accept it as final.

In practice, that means you can be paid on the decision now, even if the other side wants to fight it later.

What records win an adjudication?

The timetable is tight, so the evidence needs to exist before the dispute starts. That means your payment applications and notices, variation instructions, photos and a site diary with dates.

Many disputes start with the payment timetable. Our guide to payment applications explains how a missed notice changes the sum due. For a large or complex claim, take legal advice before you start.

Sources and further reading