Can a builder or subcontractor suspend work for non-payment?
By Dave Groom·AI-assisted·Editorial policy
Yes, on most business-to-business construction contracts. Section 112 of the Construction Act lets you suspend any or all of your work when the notified sum isn't paid by the final date for payment. You must first give at least seven days' notice saying why. Homeowner jobs are different, because the Act excludes residential occupiers.

It's a strong right, but it only works if you follow the steps exactly. Here's what the section says and where builders get caught out.
When does the right to suspend arise?
The right arises when the payer hasn't paid the notified sum by the final date for payment, as section 111 requires. The notified sum is the amount in a valid payment notice, or in your own notice if the payer didn't send one, less any amount in a valid pay less notice.
That last part matters. If the payer served a pay less notice in time, the sum you can suspend over is the lower figure in that notice.
What must the notice of suspension say?
Section 112(2) says you can't suspend without first giving the party in default at least seven days' notice of your intention, stating the ground or grounds.
Put it in writing and keep proof of delivery. A clear notice names the contract, the payment, the notified sum, the final date for payment that was missed, and the date you'll suspend if it isn't paid.
Can you suspend part of the work?
Yes. Since the 2011 amendments, the section lets you suspend "any or all" of your obligations. You could, for example, stop one package or stop supplying materials while finishing work needed to leave the site safe.
Whatever you suspend, leave the site safe and secure. Your health and safety duties don't pause with the payment dispute.
Who pays for the stoppage?
Section 112(3A) says the party in default must pay you a reasonable amount for the costs and expenses you reasonably incurred because you suspended. That can cover demobilising and remobilising, standing plant and rearranging labour.
Keep the evidence as it happens: hire invoices, labour records and diary entries, each dated.
Do you get extra time?
Yes. Section 112(4) says the period of suspension is ignored when working out any contractual time limit for completing work affected by it. If the time limit is a date, the date moves.
That protects you from delay damages for the days you weren't working because you hadn't been paid.
When does the suspension end?
The right ends when the party in default pays the sum in full. Once paid, return to site promptly and record the date you remobilised.
What if the client is a homeowner?
Section 106 says Part II of the Act doesn't apply to a contract mainly about work on a home the client lives in or plans to live in. So there's no statutory right to suspend on most domestic jobs.
Your protection there is your own contract. Write in stage payments, a right to suspend after notice and interest on late payment. Our guides to stage payments and unpaid invoices cover the domestic side.
What are the risks of getting it wrong?
If no valid notified sum was unpaid, or you didn't give seven clear days' notice, you may have no right to stop. Walking off site without that right could leave you in breach of contract yourself.
Check the dates against your contract before you send anything, and if the sums are large, take legal advice. EstiMate Pro's legal toolkit, at £39.99 a month, includes suspension notices built from the job's records (contract software).
Sources and further reading
- Housing Grants, Construction and Regeneration Act 1996, section 112 — legislation.gov.uk
- Housing Grants, Construction and Regeneration Act 1996, Part II — legislation.gov.uk